St Mary, Horton Kirby

A full programme of repairs, tendered as one and structured so the church can deliver it as funding allows.

Key Challenges

Our Solution

We tendered the full scope of repairs and structured it so it can flex with the funding available.

Our Design

Horton Kirby began as a standard Quinquennial Inspection. The parish then committed to completing all the recommended works within the five-year window, and we turned the inspection findings into a single, deliverable programme.

Rather than fix a budget upfront, we tendered the full scope of works and priced the lower-priority repointing separately, below the line. If grant funding falls short, that element can be reduced without reopening or re-pricing the rest of the programme. We ran the whole tender process on the church's behalf: drawing on experienced heritage contractors, arranging site visits, handling queries, analysing the returns and recommending the lowest compliant tender.

Two elements called for particular care:

  • The boiler room had been sealed against asbestos years ago with a low-cost cap that has since begun to fail; we drilled a trial hole to establish contamination levels ahead of proper remediation or removal.

  • The spiral stone staircase to the bell tower is worn too deeply for a conventional timber tread overlay, so we designed a bespoke timber structure to sit over the stone, protecting the historic steps while making the tower safely accessible.